Sl. No Sub No Project Name SAR FR DPR Amt
(in Cr)
AS Amt
(in Cr)
TS Amt
(in Cr)
Tender Amt
(in Cr)
Work Awarded Amt
(in Cr)
Work Expenditure Amt
(in Cr)
Physical Work Progress
(in %)
Present Status
1 Upgradation of Existing Public Toilets
   
Click for Sub projects
1.4 1.4 1.29 1.28 1.16 0.67
1.1 1 Renovation of Public Toilet at 6 Locations 0.80 0.80 0.7 0.672 0.545 0.545 Completed
Renovation of Toilets at 1) Corporation (100%) 2) Putharikhandam (100%) 3) Thambanoor Sulabh (100%), 4) KSRTC in gate (100%) 5) KSRTC out gate (100%) 6) Vanjiyoor (100%)
1.2 2 Reconstruction of Public Toilets at 3 Locations 0.6 0.6 0.59 0.605 0.61 0.12 Completed
Reconstruction of Toilets at 1) Opp. New Theatre (100 %) 2) East Fort (dropped due to Archeological NOC Issues) 3) Nr. Padmanaba Theatre (dropped due to Unwillingness of Contractor). This Two locations will be re-tendered again.
2 Drinking Water Fountains
   
Click for Sub projects
2.52 2.52 0.46 2.44 2.2 0.42
2.1 3 Installation of Drinking Water Kiosk at 25 Locations 2.52 2.52 0.46 2.442 2.2 0.4245 Execution Stage
Installation of Drinking Water Kiosks at 24 identified locations were started on 10th January 2020. Water Kiosk 12 locations completed & scheduled for inauguration: 1. Woman and Child hospital (Near Front Entrance) 2. Woman and Child hospital (Back Side) 3. Model School (Near Entrance) 4. Model School (Inside campus) 5. Putharikandam(Near Front Entrance parking area) 6. Putharikandam(In Left side Pathway) 7. Putharikandam(In Left Side Pathway) 8. Rajaji Nagar Anganwadi 9. Thampanoor UP School 10. Sreechithra Park 11. Corporation Entrance 12. Inside Gandhi Park The following locations are yet to be completed. 1. Woman and Child hospital (Near Front Entrance) 2. Woman and Child hospital (Back Side) 3. Model School (Near Entrance) 4. Model School (Inside campus) 5. Putharikandam(Near Front Entrance parking area) 6. Putharikandam(In Left side Pathway) 7. Putharikandam(In Left Side Pathway) 8. Rajaji Nagar Anganwadi 9. Thampanoor UP School 10. Sreechithra Park 11. Corporation Entrance 12. Inside Gandhi Park The following locations are yet to be completed. 1. Near Chalai New Market block- 1 2. Near Chalai New Market block- 2 3. RMS Thampanoor Bus stand 4. General Hospital Trivandrumm 5. Near SMV School 6. Opposite SBI Vazhuthacaud 7. Opposite Sweet Mahal, near leather shop at Bakery Junction 8. Near University College entrance 9. Opposite to Kanakakunnu, in front of Childrens park 10. Near Sree Chitra home entrance 11. Near Nandavanam Book stalls 12. Corporation Campus- 2
3 MLCPs cum Commercial Complexes (4 No.s)
   
Click for Sub projects
71.5 71.5 68.65 49.66 49.11 1.56
3.1 4 Construction of MLCP at Thampanoor 22.9 22.9 20.05 18.36 18.897 0.5168432 Execution Stage
Pilling (254 piles) is ongoing at site and 147 numbers completed. Building permit and Initial fire NOC received.
3.2 5 Construction of MLCP at Public Office 15.61 15.61 15.61 0.33436 DPR Stage
NHIDCL is preparing a DPR for 15.61 Cr. SCTL may consider issuing A/s for this project based on fund availability. NHIDCL has withdrawn from this project and SCTL is now entrusted to tender this work. Clarity of revenue generation is required prior to tendering
3.3 6 CONSTRUCTION OF MLCP AT A BLOCK 32.99 32.99 32.99 31.304 30.213 0.70663 Execution Stage
Received site handover from TRIDA on 13 Jan 2021. Test Pile started
4 Smart Roads
   
Click for Sub projects
563.29 563.29 501.9 519.98 530.35 12.07
4.1 7 Construction of Smart Road Phase - 1 & 2 A (PWD Roads) 142.29 142.29 124.3 134.23 136.955 3.04798 Work Awarded
Work Awarded to M/s NA Constructions. Survey works in progress
4.2 8 Construction of Smart Road Phase - 2B & 4A (Corporations Roads) 106.1 106.1 100.8 101.9 104.055 2.27262 Execution Stage
Work Award was awarded on 22 Sept 2020 and agreement has been executed. Site surveys are completed. The construction of storm water drain and the utilty duct are in progress at Fort ward (around 1.5 KM).
4.3 9 Construction of Smart Road Phase - 3 (KRFB Roads) 160.4 160.4 141.4 139.16 141.841 3.4357 Work Awarded
Work Awarded to M/s NA Constructions. Survey Works in progress
4.4 10 Construction of Smart Road Phase - 4B (PWD Roads) 154.5 154.5 135.4 144.69 147.496 3.30933 Work Awarded
Work Awarded to M/s RK Madhani and Co. Survey works in progress
5 Redesign of Bus Stops with WiFi Hotspot Facilities
   
Click for Sub projects
4.99 1.57 0.9 1 0.89 0.28
5.1 11 Construction of Smart Bus Shelter Phase - 1 (6 Locations) 1.57 1.57 0.9 1.00 0.886 0.27954 Completed
Panavila (100%) Ayurveda college (100%) Thambanoor RMS (100%) Killipalam-1(100%) Opp Womens College (100%)
6 Last Mile Connectivity (e-autos, taxi stands, bicycle sharing pods)
   
Click for Sub projects
0.8 0.8 0.8 0.84 0.8 0.86
6.1 12 Promotion of E-Mobility through procurement of 15 E - Autos 0.42 0.42 0.42 0.49 0.441 0.45895 Completed
Work completed. Vehicle supplied to the Beneficiaries
6.2 13 RFP for 15 e-Rickshaws 0.34 0.34 0.34 0.34 0.345 0.392427 Completed
Work completed. Vehicle supplied to the Beneficiaries
6.3 14 Promotion of E-Mobility through installation of Smart EV Charger 0.04 0.04 0.04 0.01 0.011 0.0133897 Completed
Work completed. EV Charger Installed at Gandhi Park East Fort
7 Redevelopment of Palayam Market
   
Click for Sub projects
127.24 127.24 84.82 92.81 91.65 2.8
7.1 15 Main Building 113.62 113.62 71.2 77.53 73.239 2.50582 Execution Stage
TRIDA has handed over the site to SCTL on 13 Jan 2021. The design is being altered to address the concerns of vendors for rehabilitation which is a prerequisite for construction of rehabilitation blocks.
7.2 16 Bio Mining of Waste Dumped at Palayam Market 0.94 0.94 0.94 1.05 0.91 0.02013 Execution Stage
80% of the waste is cleared so far. Intermittent rainfall has affected the progress of waste segregation and clearance.
7.3 17 Rehabilitation Block on TRIDA Land (using prefabricated Structures) 12.68 12.68 12.68 14.23 17.503 0.2716 Execution Stage
Work Awarded to M/s RDS Project Ltd. Fencing completed
8 Integrated Transit node (East Fort Bus stand)
   
Click for Sub projects
29.2 29.2 25.11 24.92 26.03 0.68
8.1 18 Construction of Underground Sub Way 29.20 29.20 25.11 24.918 26.0288 0.68496 Work Awarded
LOA Issued to M/s Thoppil Constructions
9 Warehouse facilities with ancillary activities at Chalai Chalai warehouse with commercial complex
   
Click for Sub projects
19.68 19.68 19.68 19.24 19.13 0.45
9.1 19 Warehouse complex at Chalai 17.62 17.62 17.62 17.18 18.655 0.405718 Execution Stage
Test Pile arrangements in progress
9.2 20 Bio Mining of Waste at Chalai 2.06 2.06 2.06 2.06 0.475 0.04412 Execution Stage
Work started.
10 OAT at Putharikandam Maidanam
   
Click for Sub projects
15.93 15.93 15.93 12.33 11.76 0.35
10.1 21 DPR of Putharikandam Maidanam & EK Nayanar Park 12.682 12.682 12.682 9.083 9.545 0.2761675 Execution Stage
Gallery works slab works in progress. Other parallel civil works going on like toilet block, theme park, rain shelter, compound wall etc.
10.2 22 Installation of Tensile Roof above Central Plaza, East Fort 3.248 3.248 3.248 3.249 2.21 0.06957 Execution Stage
11 Heritage Trails & Walks - Fašade, Wall painting & Floor Marking
   
Click for Sub projects
0.96 0.96 0.35 0.02
11.1 23 Heritage Trails & Walks - Fašade, Wall painting & Floor Marking 0.96 0.96 0.35 0.02056 TS Stage
The project will be tendered based on the progress in execution of Smart Road.
12 Interactive Information Kiosks & Display boards
   
Click for Sub projects
1.08 1.08 0.59 0.6 0.55 0.05
12.1 24 ICT Component 1 1 0.51 0.507 0.472 0.02142 Execution Stage
Content Management Software for Information Kiosk is under review.
12.2 25 Civil Component 0.08 0.08 0.08 0.09 0.074 0.0260501 Completed
1) Corporation (100 %) 2) Gandhi park (100 %)
13 Heritage Conservation - Tanks + Statue
   
Click for Sub projects
4.83 4.83 4.37 5.63 0.99 0.11
13.1 26 Temple Tanks - Puthenchanda and Sreekandeshwaram 1.45 1.45 0.99 0.95 0.99 0.0345056 Execution Stage
Work in progress. Civil works nearing completion
13.2 27 Statues at 5 Locations 3.38 3.38 3.38 4.68 0.0724 Tender Evaluation Stage
Technical Evaluation is going on
14 27 Urban Street Haat - (Charitha Veedhi)
5.81 5.81 4.11 1.99 1.99 0.12 Execution Stage
Stall Foundation works completed
15 27 Cultural streets - (Manveeyam Veedhi)
1.92 1.92 1.68 1.41 1.41 0.04 Work Awarded
Agreement executed
16 Convergence Projects
   
Click for Sub projects
271.85 271.85 271.85 271.85 271.85 212.66
16.1 28 Continous Piped Water Supply 20.55 20.55 20.55 20.55 20.55 15.93 Completed
under AMRUT Scheme
16.2 29 Under Ground Drainage Network 26.57 26.57 26.57 26.57 26.57 26.57 Completed
under AMRUT Scheme
16.3 30 Storm Water Drains - AMRUT Convergence 28.50 28.50 28.50 28.50 28.50 28.50 Completed
under AMRUT Scheme
16.4 31 Non Motorized Transport - AMRUT 18.32 18.32 18.32 18.32 18.32 0.09 Completed
16.5 32 Parks - AMRUT 3 3 3 3 3 0.3 Completed
Under AMRUT Scheme - Convergence Project
16.6 33 Renovation of Shri Anantha Padmanabhaswamy Temple Precinct (Facilities, Renovation of structures, connectivity, signage, walkways) 77.39 77.39 77.39 77.39 77.39 55.96 Completed
Under Swadesh Darshan
16.7 34 Decentralized Solid Waste Management 1.93 1.93 1.93 1.93 1.93 0.386 Completed
16.8 35 Integrated Social Housing Complex - Rajaji Nagar - PMAY 47.95 47.95 47.95 47.95 47.95 47.95 Completed
16.9 36 Kerala Portal , SSDG, E-District 47.64 47.64 47.64 47.64 47.64 36.97 Completed
Under Kerala State IT Mission
17 Linked Green Activity Zones and Pedestrian Streets
   
Click for Sub projects
4.43 4.43 3.36 3.5 3.3 0.39
17.1 37 DPR/ RFP for Phase 1: Open Gym 0.42 0.42 0.41 0.44 0.352 0.2978234 Completed
Work Completed - Inauguration Done
17.2 38 DPR/ RFP for Phase 2: Ponnara Sredharan Park 1.03 1.03 1.02 1.14 1.02 0.02324 Execution Stage
Work completed at following locations:
1) Ponnara Sreedhara Park
17.3 39 Childrens park (KWA) 2.98 2.98 1.93 1.92 1.923 0.0655594 Execution Stage
Civil works in progress
18 Sustainable Campuses (Solar Rooftop, Rainwater harvesting and Public Bike Sharing)
   
Click for Sub projects
4.97 4.97 8.34 4.89 4.05 0.67
18.1 40 DPR/ RFP for Solar Roof top 4.11 4.11 7.48 4.10 3.37 0.6539097 Execution Stage
Site Inaugurated. EXECUTION at below Locations - 1) Kerala Legslative Assembly. 2) University Library. 3) Central Library. 4) Womens College 5) Central School & Smart City Thiruvananthapuram Limited
18.2 41 DPR/ RFP for Rain Water Harvesting 0.86 0.86 0.86 0.79 0.68 0.01842 Execution Stage
Execution by Kudumbasree Locations: 1) Womens College Vazhuthacaud
2) Corporation Office, Palayam
19 Integrated Social Housing Complex - Rajaji Nagar
   
Click for Sub projects
60.88 60.88 59.42 57.78 61.42 1.32
19.1 42 Rajaji Nagar 60.88 60.88 59.42 57.78 61.417 1.3206149 Execution Stage
Work awarded to M/s Silpa Projects and Infrastructure. Survey works in progress
20 Upgradation of Anganwadis & Public Health Centres
   
Click for Sub projects
2.77 2.77 2.25 2.14 2.23 0.38
20.1 43 Anganwadi at Sanskrit School, Fort, Thampanoor UP School, Rajaji Nagar 0.71 0.71 0.48 0.43 0.428 0.3300951 Completed
Inaugurated the Site
20.2 44 PHC Rajaji Nagar 2.06 2.06 1.77 1.71 1.805 0.0451348 Execution Stage
Test piles completed
21 Vending zones at RKV Road
   
Click for Sub projects
2.78 2.78 1.97 1.92 2.02 0.06
21.1 45 Vending zones at RKV Road 2.78 2.78 1.97 1.92 2.02 0.0597375 Execution Stage
Site Clearance and Surevey work in progress
22 Centralised Command Control Centre
   
Click for Sub projects
92.21 92.21 89.02 96.56 96.05 1.98
22.1 46 ICCC - Building 7.34 7.34 4.15 1.33 1.372 0.1648351 Execution Stage
work started by M/s BRK Constructions
22.2 47 ICCC - Software & Hardware 84.87 84.87 84.87 95.23 94.68 1.81788 Work Awarded
Work Awarded to M/s NEC Technologies
23 47 Smart Mosquito Density System
0.54 0.62 0.63 0.54 0.54 0.01 Execution Stage
Installation of 4 devices completed and Pilot Go-Live started
24 47 TSCCC + ATCS
68.59 68.59 68.58 68.59 64.28 1.47 Execution Stage
Site Survey of Pilot 20 Locations in progress