Projects- Current Financial Year (2019-2020)

Description Amount
(in Cr)
% SCP Cost % AS Amount
Total SCP Modules: 43 1538.2
Detailed Project Report 1318.11
85.69%
A/s Accorded 1298.75
84.43%
T/s Issued 970
63.06%
74.69%
Tendered 935.73
60.83%
72.05%
Work awarded 184.02
11.96%
14.17%
Work Completed 174.04
11.31%
13.4%
Expenditure 174.04
11.31%
13.4%

Project Progress ( in INR Cr)

Grant Allocatted Vs Received (in INR Cr)

Total expenditure incurred against Smart City fund allocation (In INR Crores)

Total expenditure incurred against Smart City fund allocation (In percentage)