Projects- Current Financial Year (2019-2020)

Description Amount
(in Cr)
% SCP Cost % AS Amount
Total SCP Modules: 43 1538.2
Detailed Project Report 1309.23
85.11%
A/s Accorded 1309.23
85.11%
T/s Issued 1160.22
75.43%
88.62%
Tendered 1130.4
73.49%
86.34%
Work awarded 386.11
25.1%
29.49%
Work Completed 118.91
7.73%
9.08%
Expenditure 118.91
7.73%
9.08%

Project Progress ( in INR Cr)

Grant Allocatted Vs Received (in INR Cr)

Total expenditure incurred against Smart City fund allocation (In INR Crores)

Total expenditure incurred against Smart City fund allocation (In percentage)