A13-Last Mile Connectivity (e-autos, taxi stands, bicycle sharing pods)

Promotion of E-Mobility through installation of Smart EV Charger

Project Details

Estimated Cost
(In Rs. Cr)
Smart City Grant
(In Rs. Cr)
PPP
(In Rs. Cr)
ULB Fund
(In Rs. Cr)
Central Scheme
(In Rs. Cr)
1.92 1.92 0 0 0

Ward Name & No. Project Status SCTL Official in Charge PMC Official in Charge
ABD Area Completed
Work completed. EV Charger Installed at Gandhi Park East Fort
Sam K Panicker

Project Progress

Physical Work % Financial progress %
100 % %
Administrative Sanction
Amount Order No Date Status
0.04 SCTL/TECH/7/2020/AM-E/1 28/05/2020 Issued
DPR Details
Amount Type: Doc. No & Date Status
0.04
N/a

Technical Sanction
Amount Order No & Date Status
0.04 N/a N/a
Tender Details
PAC Amount Start Date End Date Pre Bid Date Status
0.01 5-06-2020 29-06-2020 Closed
Execution Details
Work Award Amount Project Expenditure Executing Agency Start Date End Date Status
0.011 0.01 Powerzone Service Solutions LOA issued on 30-Jun-2020
Phy Progress Fin Progress
100 % 100 %

PROJECT COMPONENTS/DESCRIPTION