A5-Upgradation of Existing Public Toilets

Renovation of Public Toilet at 6 Locations

Project Details

Estimated Cost
(In Rs. Cr)
Smart City Grant
(In Rs. Cr)
PPP
(In Rs. Cr)
ULB Fund
(In Rs. Cr)
Central Scheme
(In Rs. Cr)
1.41 0.35 0 0 1.05

Ward Name & No. Project Status SCTL Official in Charge PMC Official in Charge
ABD Area Completed
Renovation of Toilets at 1) Corporation (100%) 2) Putharikhandam (100%) 3) Thambanoor Sulabh (100%), 4) KSRTC in gate (100%) 5) KSRTC out gate (100%) 6) Vanjiyoor (100%)
Jerry Jose Shameena

Project Progress

Physical Work % Financial progress %
100 % 80 %
Administrative Sanction
Amount Order No Date Status
0.80 SCTL/PRJ-205-2018-1 17-09-2019 Issued
DPR Details
Amount Type: Doc. No & Date Status
0.80
IPE/SCTL-PMC-PD-DPR-01
02-02-2019
Technical Sanction
Amount Order No & Date Status
0.7 TS-Toilet-01 TS-Toilet-02 6th Oct 201830th Oct 201830th Oct 201830th Oct 201830th Oct 201830th Oct 30th Oct 2018 Completed
Tender Details
PAC Amount Start Date End Date Pre Bid Date Status
0.672 26th Nov 2018 5th Jan 2019 N/a Complete
Execution Details
Work Award Amount Project Expenditure Executing Agency Start Date End Date Status
0.545 0.24 M/s Sulabh dtd 6th Jan 2020, M/s Kudumbasree 31st Jan 2020 01/14/2020 30 Dec 2020 Completed
Phy Progress Fin Progress
100 % 43.39 %

PROJECT COMPONENTS/DESCRIPTION

Six exisiting public toilets within ABD area are considered for upgradation. Selected public toilets are Corporation Campus PC station, Putharikandam Maidanam PC station, Thampanoor KSRTC outgate and ingate toilets, Vanchiyoor Sulabh PC station and Thampanoor Sulabh PC station