A7-Drinking Water Fountains

Installation of Drinking Water Kiosk at 25 Locations

Project Details

Estimated Cost
(In Rs. Cr)
Smart City Grant
(In Rs. Cr)
PPP
(In Rs. Cr)
ULB Fund
(In Rs. Cr)
Central Scheme
(In Rs. Cr)
7.32 7.32 0 0 0

Ward Name & No. Project Status SCTL Official in Charge PMC Official in Charge
ABD Area Execution Stage
Installation of Drinking Water Kiosks at 24 identified locations were started on 10th January 2020. Water Kiosk 12 locations completed & scheduled for inauguration: 1. Woman and Child hospital (Near Front Entrance) 2. Woman and Child hospital (Back Side) 3. Model School (Near Entrance) 4. Model School (Inside campus) 5. Putharikandam(Near Front Entrance parking area) 6. Putharikandam(In Left side Pathway) 7. Putharikandam(In Left Side Pathway) 8. Rajaji Nagar Anganwadi 9. Thampanoor UP School 10. Sreechithra Park 11. Corporation Entrance 12. Inside Gandhi Park The following locations are yet to be completed. 1. Woman and Child hospital (Near Front Entrance) 2. Woman and Child hospital (Back Side) 3. Model School (Near Entrance) 4. Model School (Inside campus) 5. Putharikandam(Near Front Entrance parking area) 6. Putharikandam(In Left side Pathway) 7. Putharikandam(In Left Side Pathway) 8. Rajaji Nagar Anganwadi 9. Thampanoor UP School 10. Sreechithra Park 11. Corporation Entrance 12. Inside Gandhi Park The following locations are yet to be completed. 1. Near Chalai New Market block- 1 2. Near Chalai New Market block- 2 3. RMS Thampanoor Bus stand 4. General Hospital Trivandrumm 5. Near SMV School 6. Opposite SBI Vazhuthacaud 7. Opposite Sweet Mahal, near leather shop at Bakery Junction 8. Near University College entrance 9. Opposite to Kanakakunnu, in front of Childrens park 10. Near Sree Chitra home entrance 11. Near Nandavanam Book stalls 12. Corporation Campus- 2
Gayathri Joseph

Project Progress

Physical Work % Financial progress %
70% % %
Administrative Sanction
Amount Order No Date Status
2.52 SCTL/PRJ/220/2019/UD/1 27/10/2018 Sanctioned
DPR Details
Amount Type: Doc. No & Date Status
2.52
IPE-SCTL/PMC/PD/DPR/05a
27/10/2018
Technical Sanction
Amount Order No & Date Status
0.46 TS/Drinking-01 dtd 2th Nov 2018 Sanctioned
Tender Details
PAC Amount Start Date End Date Pre Bid Date Status
2.442 7th Sep 2019 5th Oct 2019 N/a Completed
Execution Details
Work Award Amount Project Expenditure Executing Agency Start Date End Date Status
2.2 0.46 M/s Oasis WFS(P) Ltd 01/10/2020 03/31/2020 W/o dtd 19th Nov 2019, Completion - 75 Days
Phy Progress Fin Progress
70 % 20.91 %

PROJECT COMPONENTS/DESCRIPTION

This project aims at making potable water available at 25 locations throughout the ABD area.

Project progress is 70%.