B18-Integrated Transit node (East Fort Bus stand)

Construction of Underground Sub Way

Project Details

Estimated Cost
(In Rs. Cr)
Smart City Grant
(In Rs. Cr)
PPP
(In Rs. Cr)
ULB Fund
(In Rs. Cr)
Central Scheme
(In Rs. Cr)
54.51 43.61 10.9 0 0

Ward Name & No. Project Status SCTL Official in Charge PMC Official in Charge
Fort, 18 Work Awarded
LOA Issued to M/s Thoppil Constructions
Vishnu Venugopalan Abraham

Project Progress

Physical Work % Financial progress %
% %
Administrative Sanction
Amount Order No Date Status
29.20 15th Board Meeting 06.10.2020 Issued
DPR Details
Amount Type: Doc. No & Date Status
29.20
PMC/PD/PP-2/DPR-09
7th Feb 2020
Technical Sanction
Amount Order No & Date Status
25.11 TS/East Fort - 04, 04/09/2020 Received
Tender Details
PAC Amount Start Date End Date Pre Bid Date Status
24.918 04.11.2020, Wednesday 23.11.2020, Monday Re Tendered
Execution Details
Work Award Amount Project Expenditure Executing Agency Start Date End Date Status
26.0288 0.06 M/s Thoppil Constructions loa issued on 31-1-2021
Phy Progress Fin Progress
% 0.23 %